Project Summary:

Fristly, enabling works completed to allow housing contractor onto site. This enabling package included a large 278 package in
which we had to tie in the new road into an existing roundabout on a busy road in Chesterfield. Secondly, we installed the
SW & FW drainage system along with all the roads & road crossings, inc tarmac, or Phase 1 of the development.