Two large commercial units on the same plot including 278 package which encroached on the access/egress of a Fire Station causing logistical challenges. On site, large SW system
which consisted of a very tricky off site connection through public footpaths and into the existing drainage network. Large diameter concrete pipes and catchpits used on site for attenuation. Deep FW system to both units. Package included Section 38 access road and turning circle