Client: JF Finnegan

white icon

Start Date: February 2018

white icon

Project Value: ££1.5m

white icon

Deliverables: New facility

white icon

Project Summary:

New facility built at the side of an existing unit which allowed access via rail for track load/off load and storage of steel coil material. SW and FW drainage systems, Attenuation tank and large electricity capacity Sub Station & feed which needed to be bought onto site from the main road. High spec drainage channels and concrete work to the inside of the unit including a bunded wall.