Client: GMI

white icon

Start Date: September 2021

white icon

Project Value: ££4m

white icon

Deliverables: Bottling Plant/Facility

white icon

Project Summary:

One of the first facilities of its kind in the UK. 3 types of Drainage systems – Foul Water, Surface Water and a specialist CPV pipework & preformed CPV manhole system with fusion welded joints (all
done in house) to accommodate high temperature and contaminated liquids. Installation of vertical Effluent Tanks, interceptors, headwalls and forming of attenuation ponds.